Status: Ongoing
Country: Jordan
Issue
The municipalities of Ramtha and Sahel Houran in northern Jordan faced pressing sanitation challenges. Limited wastewater network coverage, outdated infrastructure, and insufficient treatment capacity created environmental risks, public health concerns, and hindered sustainable development. Vulnerable households were particularly affected, with many lacking proper connections to the sewer network.

Initiative
Under funding from the French Development Agency and the European Union, the Water Authority of Jordan launched a comprehensive sanitation program in Ramtha and Sahel Houran, implemented by SAJDI in collaboration with international and local partners.
The program includes:
- Connection of vulnerable households: Around 3,200 households (serving ~24,000 residents) will be connected to the wastewater network.
- Wastewater network expansion: Installation of approximately 160 km of pipelines and 4 pumping stations to serve 200,000 people by 2030.
- WWTP upgrade and treated water transfer: Extension of Ramtha Wastewater Treatment Plant by 11,000 m³/day and an 8 km treated water transmission line to Shalallah WWTP for agricultural reuse.
SAJDI’s role spans from feasibility studies, environmental and social impact assessments, and detailed engineering design, to tender preparation, construction supervision, and overseeing operation and maintenance.
Benefits
- Significantly improved access to wastewater services.
- Enhanced public health through modern sanitation infrastructure.
- Increased reuse of treated wastewater for agriculture.
- Protection of water resources and the environment.
- Strengthened resilience and sustainability of the region’s infrastructure.
Specializations used:
- Feasibility Studies & Preliminary Engineering
- ESIA (Environmental & Social Impact Assessment)
- Detailed Engineering Design & Tender Documentation
- Construction Supervision
- Operation & Maintenance Oversight